AGENDA
NETC ADVISORY COMMITTEE MEETING
DATE: March 28, 2017
TIME: 11:00 a.m. – 12:00 p.m.
LOCATION: Conference Call 1-866-906-7447
Participant Access Code 8626283
AGENDA ITEMs
Call to Order
Open Projects
Project # and Title | PI, University
AC Liaison |
Update | End Date |
13-1: Development of High Early-Strength Concrete for Accelerated Bridge Construction Closure Pour Connections | Brena,
UMass Amherst
C. Bradley |
PI completed 90% of the project, but two tests remain. PI in communication with TAC chair and scheduling a TAC meeting. | 1/14/17
(NCE) |
13-2: HMA Mixtures Containing Recycled Asphalt Singles (RAS): Low Temperature Fatigue Performance of Plant-Produced Mixtures | Mogawer,
UMass Dartmouth
A. Scholz |
Since contractors have not yet provided PCAS mixtures, PI obtained PCAS to work on two mixture design. PI continues test PCAS mixtures and MSW mixtures. | 12/1/17 (NCE) |
13-3: Improved Regionalization of Quality Assurance (QA) Functions | Dave,
UNH
C. Franco |
DOTs working with VTrans to use existing SharePoint site to share QA data. PI and TAC will work to identify pilot projects to use tool. | 4/2/17 (NCE) |
14-2: Investigation of Northern Long-Eared Bat Roosting Sites on Bridges | Civjan,
UMass Amherst
D. Peabody |
PI held two training events to present results and get feedback on research and feasibility of draft bridge survey form. PI provided draft report to TAC for review and edits. | 5/31/17
(NCE) |
15-1: Use of Forested Habitat Adjacent to Highways by Northern Long Ear Bats | Foster,
UNH
D. Peabody |
Contract in process between UVM and UNH.
Coordinator contract extension received and contract processes moving forward. |
TBD |
15-2: Using the New SHRP2 Naturalistic Driving Study Safety Databases to Examine Safety Concerns for Older Drivers | Samuel,
UMass Amherst
D. Peabody |
Contract fully executed between UMass Amherst and UVM. PI working with VTTI on data request. | 12/31/18 |
15-3: Moisture Susceptibility Testing for Hot Mix Asphalt Pavements in New England | Dave,
UNH
D. Peabody |
Contract between UVM and UNH fully executed. PI has begun literature review. PI held kick-off meeting to discuss research plan and scheduling. PI sending survey to identify mixtures and projects for 2017 construction season. | 7/31/18 |
*Final Tech Transfer Items: Currently these include the final report to the TAC; a “Fact Sheet” summary – NETC template; a presentation to the TAC and other interested DOT participants that is recorded by NETC and made available. |
NETC Advisory Committee Discussion of Research Topics
- New England roundabouts
- Have received NH, CT, ME and RI TAC member
- Please send names and contact information for TAC members
- Implement recommendations on Effective Establishment of Native Plants on Roadsides
- Have received support from ME and CT TAC members
- Please send any additional names and contact information for TAC members
NETC New England Networks Inventory
- Please return to Coordination Team by 4/14/2017
Other Business
- Region 1 UTC has not been awarded
- The new solicitation has not yet been issued, but the Coordinator will inform the advisory committee when it is issued
- NETC Program Review Follow-up April 12, 2017 10 AM -12PM
- NETC Program Review In-person meeting to be scheduled for June (except week of June 12th )
- NETC Advisory Meeting Next Monthly Meeting – April 25, 2017, 11 AM – 12 PM
Adjourn