Project # and Title | PI, University
AC Liaison |
Update | End Date |
10-3: Low Temperature and Moisture Susceptibility of RAP Mixtures with Warm Mix Technology | Mogawer,
UMass Dartmouth
A. Scholz |
PI continued to analyze mixtures tested to date. The PI has not yet received high RAP mixtures prepared using foaming as the WMA technology.
|
5/31/17
(NCE) |
13-1: Development of High Early-Strength Concrete for Accelerated Bridge Construction Closure Pour Connections | Brena,
UMass Amherst
C. Bradley |
PI completed 90% of the project, but three tests remain. | 1/14/17
(NCE) |
13-2: HMA Mixtures Containing Recycled Asphalt Singles (RAS): Low Temperature Fatigue Performance of Plant-Produced Mixtures | Mogawer,
UMass Dartmouth
A. Scholz |
Since contractors have not yet provided PCAS mixtures, PI obtained PCAS to work on two mixture design. PI continues test PCAS mixtures and MSW mixtures. | 12/1/17 (NCE) |
13-3: Improved Regionalization of Quality Assurance (QA) Functions | Dave,
UNH
C. Franco |
DOTs working with VTrans to use existing SharePoint site to share QA data. PI and TAC will work to identify pilot projects to use tool. Meeting expected shortly. | 4/2/17 (NCE) |
14-2: Investigation of Northern Long-Eared Bat Roosting Sites on Bridges | Civjan,
UMass Amherst
D. Peabody |
PI working scheduling two training events for the week of March 13 – 17 in NH (ME and VT will attend) and MA (CT and RI will attend). The training will be recorded. NCE in process between UVM and UMass. | 4/17/17 |
14-4: Optimizing Future Work Zones in New England for Safety and Mobility | Xie,
UMASS Lowell
C. Bradley |
PI requested additional data from VTTI, which may delay analysis. | 7/5/17 |
15-1: Use of Forested Habitat Adjacent to Highways by Northern Long Ear Bats | Foster,
UNH
D. Peabody |
Contract in process between UVM and UNH. Coordinator contract extension required to execute contract with full 24 month project plan. | TBD |
15-2: Using the New SHRP2 Naturalistic Driving Study Safety Databases to Examine Safety Concerns for Older Drivers | Samuel,
UMass Amherst
D. Peabody |
TAC would like colleagues from FHWA Safety Training and Analysis Center and Penn State to participate as non-voting advisers. Contract in process UMass Amherst and UVM. Coordinator contract extension required to execute contract with full 24 month project plan. | TBD |
15-3: Moisture Susceptibility Testing for Hot Mix Asphalt Pavements in New England | Dave,
UNH
D. Peabody |
Contract between UVM and UNH fully executed. PI has begun literature review. PI scheduled kick-off meeting for March 6, 2017. | 7/31/18 |
15-4: Optimizing Quality Assurance (QA) Processes for Asphalt Pavement Construction | Awaiting final 13-3 report (expected Spring 2017) to inform this. | ||
*Final Tech Transfer Items: Currently these include the final report to the TAC; a “Fact Sheet” summary – NETC template; a presentation to the TAC and other interested DOT participants that is recorded by NETC and made available. |
NETC Fund Balance Update
- All previous fund transfers have been completed or are in process with FHWA
- FY2017 Fund Balance Transfers – Decision deferred
- NETC Fund Balance as of 12/31/2018– $116,257.69 (without FY17 contributions, and without additional activities)
NETC Advisory Committee Discussion of Research Topics
- Rumble Strips
- New England roundabouts
- Implement recommendations on Effective Establishment of Native Plants on Roadsides
- Additional Topics?
NETC New England Networks Inventory
- Questions regarding formatting or content
- Consider sending to University and other Partners?
- Please return to Coordination Team by 3/28/2017
Other Business
- NETC Program Review Follow-up to be scheduled for mid-March
- NETC Program Review In-person meeting to be scheduled for June
- NETC Advisory Meeting Next Monthly Meeting – March 28, 2017, 11 AM – 12 PM